Defence & Security, Ukraine, Defence Investment
Ukraine Defence Infrastructure: New Rules for Private Investors
Ukraine allows private developers to build protected underground defence facilities. CORVUS examines the legal framework, 25% rule and investor risks.

Complex law. Clear action.
Reviewed by Oleksandr Sobovyi, Founder & CEO of CORVUS AI — editorial responsibility statement below.
Ukraine has introduced a legal mechanism allowing private developers and investors to finance and construct protected underground production facilities for its defence industry under simplified construction procedures.
The changes, introduced by Cabinet of Ministers Resolution No. 1304 of 21 October 2026, amend Resolution No. 1494 of 19 November 2025. They extend an existing experimental construction framework to legal entities that are not themselves defence manufacturers.
For investors, the central feature is the ability to retain commercial use of part of a development while making production space available to an eligible Ukrainian defence enterprise.
However, participation depends on meeting specific statutory conditions. The simplified construction procedure does not guarantee an investment return, government purchase or compensation.
1. A new investment model for protected defence infrastructure
Under the amended framework, a private legal entity may develop underground production facilities using its own capital or external financing.
The completed property, or part of it, must subsequently be transferred to an eligible defence industry enterprise through ownership, a lease or another legally recognised property right.
Where only part of the completed facility is transferred, at least 25% of the total construction area must be allocated to the defence enterprise and must be suitable for its manufacturing operations.
The remaining area, potentially up to 75%, may be used for the developer's investment or commercial activities, subject to the applicable law and the property's legal status.
This creates a potential model for combining defence production and commercial infrastructure within one development.
The 25% threshold is an eligibility condition, however, rather than a general authorisation to develop commercial property through exceptional construction procedures. The project must genuinely satisfy the requirements governing underground defence production infrastructure.
2. Who can participate?
The developer does not need to hold Defence City residency or already be a contractor under a Ukrainian defence procurement agreement.
It must act as a legal entity undertaking construction in its own name, at its own risk and with its own or borrowed funds.
The associated defence enterprise, however, must satisfy at least one qualifying condition under Resolution No. 1494. These include Defence City residency, inclusion in the relevant statutory list, registration as a participant or contractor in the applicable state-contract register, or designation by the Ministry of Defence as critically important for defence-related purposes.
The framework also restricts participation by legal entities with prohibited connections to an aggressor or occupying state, including specified ownership or beneficial ownership relationships.
Relevant Ukrainian and international sanctions must be considered. The developer must document its compliance with the applicable eligibility requirements.
CORVUS assessment: For cross-border investors, corporate and beneficial ownership due diligence should precede land acquisition, financing commitments and contractual negotiations. The general permission for another legal entity to act as developer does not remove other applicable foreign investment, corporate or security requirements.
3. What construction procedures are simplified?
Resolution No. 1494 provides a special construction regime covering underground manufacturing infrastructure and above-ground structures functionally connected with it.
Within the defined scope, construction may proceed without certain ordinary urban planning documents, construction authorisations and environmental impact assessment procedures. It may also proceed before completion of the usual land acquisition or allocation formalities, subject to specific conditions.
The framework provides for the use of Ukraine's Unified State Electronic System in the Field of Construction without public disclosure of the relevant project information on its portal.
These exemptions are significant for facilities requiring rapid construction or relocation.
They are not a general exemption from construction safety obligations. Project design, expert examination where legally mandatory, technical supervision and compliance with applicable construction requirements remain relevant.
The developer must also establish its legal authority to act as the construction client.
Importantly, the simplified regime does not extend automatically to unrelated commercial buildings merely because they form part of an investment portfolio.
4. The contract determines the project's financial viability
A civil-law agreement between the developer and an eligible defence enterprise is a mandatory condition for using the mechanism. It must be concluded before construction works begin.
The agreement must establish the intended facility, the developer's construction and transfer obligations, the legal right granted to the defence enterprise, the relevant area and its industrial suitability, the transfer arrangements and the intended production use.
Where the enterprise receives the property under a lease or another fixed-term right of use, the initial term must be at least one year.
The enterprise must also have the right to demand an extension of that use until martial law is terminated or lifted.
This requirement has substantial commercial implications. It can affect financing assumptions, the developer's ability to recover possession, the projected holding period and the expected return on investment.
Resolution No. 1494 does not require the Ukrainian Ministry of Defence to purchase the facility or reimburse the developer's construction expenditure.
Investors must therefore establish their own contractual basis for recovering capital and generating revenue.
From a legal structuring perspective, particular attention should be paid to payment obligations, allocation of construction cost overruns, completion risk, insurance, damage to the facility, property rights, contractual remedies and the consequences of prolonged martial law.
These additional issues require commercial agreement and project-specific legal assessment; they are not resolved automatically by the simplified procedure.
5. Ministry of Defence review and implementation
The amended procedure establishes a preliminary documentation review.
At least one month before the proposed signing date, the developer must submit the draft agreement and documentary evidence of compliance with the applicable developer eligibility requirements to the Ministry of Defence.
The Ministry has five working days from receipt to examine the submitted documentation and communicate the result.
Where deficiencies are identified, the Ministry must indicate the relevant non-compliance and how it should be addressed. The period allowed for correction must be at least five working days.
Until identified deficiencies are remedied, the special procedure cannot be applied to the construction concerned.
The Ministry's review is not equivalent to technical approval of the project and does not replace any mandatory examination of construction documentation.
Once the relevant conditions have been fulfilled and the agreement concluded, construction may proceed under the applicable simplified rules.
Commissioning remains subject to the special procedures established by Resolution No. 1494, including the required declaration or certificate, as applicable.
6. The overlooked issue: land rights after martial law
One of the most consequential legal questions concerns land.
The special regime allows certain construction activities before ordinary land acquisition, withdrawal or allocation procedures have been completed. This requires the relevant consent or approval, depending on whether the land is privately, state or municipally owned.
Such approval does not replace the developer's separate obligation to establish its authority to act as construction client.
The framework also anticipates further land regularisation after martial law ends.
Where construction is undertaken by another legal entity acting as developer, the relevant land acquisition, withdrawal or allocation costs must also be financed by that entity, without state or local budget funding.
This creates a potential long-term liability that investors should incorporate into their initial financial model.
A project may be technically completed and operational while still requiring subsequent land-related legal procedures.
For investors, the timing, cost and allocation of those obligations should be addressed before financial close.
7. What European investors should assess before committing capital
The framework may be relevant to European developers, industrial infrastructure investors and companies considering joint projects with Ukrainian defence manufacturers.
It creates opportunities for protected manufacturing facilities, industrial relocation and infrastructure development supporting defence production.
Nevertheless, a project should pass legal and financial due diligence before investment commitments are made.
The initial review should establish:
Counterparty eligibility: whether the proposed defence enterprise qualifies under Resolution No. 1494 and whether the developer satisfies the ownership and sanctions restrictions.
Property and construction rights: whether the selected site is suitable, the necessary approvals can be obtained and the developer has authority to act as construction client.
Commercial structure: whether the proposed ownership, lease or other property-right arrangement provides a defensible route to recover invested capital.
Regulatory exposure: whether security, confidentiality, sanctions, procurement, export-control or other sector-specific requirements arise from the actual project and its participants.
Long-term obligations: how extended wartime use, construction risks, subsequent land regularisation and exit arrangements will affect the investment.
For cross-border projects, the Ukrainian construction framework should be considered together with any applicable EU and national requirements governing the investor, financing arrangements and relevant technology transfers.
These are separate compliance questions and should not be treated as automatically resolved by Resolution No. 1494.
8. CORVUS perspective: structuring investable defence infrastructure
Ukraine's amended construction regime provides a legal route for private capital to support protected defence production without requiring every infrastructure investor to become a defence manufacturer.
Its commercial success will depend on the structure of individual projects.
In particular, investors need clarity on eligibility, the enforceability of property rights, the allocation of development risk and the arrangements for recovering their investment.
For European participants, these considerations must also be reconciled with the regulatory obligations applicable in their home jurisdictions.
CORVUS AI supports legal and regulatory assessment of EU–Ukraine industrial cooperation, including counterparty due diligence, contractual structuring, regulatory compliance, sanctions and export-control risk assessment.
The objective is to establish whether a proposed investment can proceed on legally defensible and commercially workable terms.
Disclaimer
This article has been prepared by CORVUS AI for general informational and educational purposes only. It is intended to make complex legal and regulatory developments easier to understand.
It does not constitute legal advice and does not create a professional adviser–client relationship. The information should not be relied upon as a substitute for advice based on the specific facts, circumstances and applicable law relevant to your organisation or project.
The article reflects our understanding of the law and regulatory framework as of the date of publication. Legislation, case law, regulatory guidance and administrative practice may subsequently change. While reasonable care has been taken in preparing this article, CORVUS AI does not warrant that the information is complete or remains current after the date of publication. We do not undertake to update this content.
To the fullest extent permitted by applicable law, CORVUS AI excludes liability for loss arising from reliance on this article. Nothing in this article constitutes an offer or solicitation to provide regulated legal services in any jurisdiction where doing so would be unlawful.
AI-assisted preparation: This article was prepared with the assistance of AI tools. Its legal analysis, conclusions and final text were subject to human review and editorial control and were reviewed and approved prior to publication by Oleksandr Sobovyi, Founder & CEO of CORVUS AI. CORVUS AI retains editorial responsibility for the published content.
For advice tailored to your organisation, project or specific circumstances, please contact CORVUS AI.
Legal sources
This article provides general legal and regulatory information as at 17 November 2026 and does not constitute legal advice on a particular transaction.